Download our free iPhone app from iTunes & Android Download Business MattersView our latest Events Become a memberThe ROCCO Awards Book a meeting room - price guarantee
Share |

Chamber News

Employer Invite to MA Evening Event
Tuesday 15th May 2012
more


Glasgow Airport Reports Increase in Passenger Numbers For April 2012
Tuesday 15th May 2012
more


Quality Assurance Certification for IQA
Tuesday 15th May 2012
more


 


Chamber Events

Royal Navy Presentation Event
Friday 25th May 2012..more


Taking on Talent (event part of Modern Apprenticeship Week)
Tuesday 22nd May 2012..more


Doing Business In China
Tuesday 29th May 2012..more



Member Events

St Vincent's Hospice 5 A-Side Charity Event
Sunday 3rd June 2012 ...more


Barbados Trade Mission
Wednesday 14th June 2012 ...more


Barbados Trade Mission
Wednesday 14th June 2012 ...more




 



Business Recycling & Reuse Directory
Collections Recycling Centres


Help   Advanced Search

 

Healthy Working Lives

M8 back to three lanes at Glasgow Airport

Thursday 12th January 2012
Transport Scotland

Drivers using the M8 near Glasgow Airport will see all three lanes temporarily re-open from today (Thursday 12th January), following the completion of the first stage of essential strengthening works.

Traffic management has been in place since Boxing Day while essential works were undertaken to bring the White Cart Viaduct bridge up to modern standards. 

The White Cart Viaduct carries the M8 over the White Cart Water immediately to the south of Glasgow Airport, and is a principal route to the airport.

Lane closures have inevitably resulted in delays in the past fortnight but this is expected to improve as day-time restrictions are lifted. 

Work will continue in the carriageway during the night (8pm-6am) and two lanes will be closed in each direction at this time.

Further work is still required on the bridge and from around 16th February, contraflow will be in operation (one lane will be closed in each direction).  These restrictions are expected to last until April.

A Transport Scotland spokesperson said: “We are delighted that the first stage of these works has gone well and that we are able to get the M8 back up to three lanes in this area until the next stage commences in February.

“Bridges like any other structure have a finite life-span and must be maintained and upgraded so we appreciate the patience of motorists during this time.  We are aiming to have the strengthening and refurbishment fully completed by Spring, at which point the route will revert to 60 miles per hour.” BAM Nuttall

The 40mph temporary speed limit will remain in place until work is fully complete by Spring and will continue to be enforced by the average speed cameras. This is to both support the safety of roadworkers during the overnight closures and provide a margin of safety to road users, as a number of temporary carriageway reinstatements, an integral part of the overnight works programme will be visible to drivers.

The White Cart Viaduct was built in 1968 and now carries over 90,000 vehicles daily. These essential strengthening works are unavoidable and on completion will ensure the bridge is brought up to modern standards and can comply with current loading and safety requirements.

This is the third phase of a £30m programme of works to upgrade the White Cart Viaduct and is being undertaken by BAM Nuttall.

This will be followed up with phase four to repaint the external steelwork of the box girders, undertake concrete repairs and below deck maintenance work.  No traffic management will be required for this phase.  Estimated completion of the full programme of works is 2016.

Motorists using the M8  can access up to the minute journey time information at www.trafficscotland.org.  Further journey planning information is also available on Twitter and via the Travelline Scotland/Transport Scotland travel app.

 